Ballasted Systems AFS 130 AFS 200 AFS 255 LT AFS 350 AFS 400 AFS 600 AFS 1300 AFS 1350 AFS 1400 AFS 1700 AFS 1800 AFS 3000 Direct Embedment Poles 25ft-80ft Hydraulic Tilt-Up Poles 25ft-150ft Conventional Poles Raising Systems Hydraulic Rams Screw-Jacks Gin Poles Antenna Mounts 36" Dual Platform T-Arm 20" Dual T-Arm 20" Universal Pipe 12"-24"-36" T-Arms and CollarsRooftop Ballasted Mounts
5'/1.5m Rooftop Ballasted 6.5'/2m Rooftop Ballasted Accessories Adjustable Grate Platform Standing Platform Pedestal Cabinet Chain Link Fencing Kit 5 Rung Ladder (AFS 1100 - 1300) 7 Rung Ladder (AFS 1700 - 3000) Chain Mount Ladder Pole Jacking Bracket Tuf-Tug Safety Cables Climbing Pegs Anchor Bolts AFS Bolt SetsHistorically Sensitive Site: Crown Castle's Communication Antenna Project
Crown Castle was in need of instillation of communication antennas in a historically sensitive site.
AFS 1300
The Need
Crown Castle needed to install communication antenna on a 90’ pole in a historically sensitive site. In addition, the site had a small footprint and accessible only over a wooden bridge with a maximum weight of 8 tons. ARE’s foundation and pole system also needed to meet local requirements for aesthetics and paint color.
Overview
Thanks to its Hydraulic System, ARE’s AFS 1300 system can be installed without a crane, in tight spaces, and with limited impact on the environment. Foundation and pole pieces were ferried across the bridge and assembled on site. ARE’s crew installed the system in a 3 days which included OSHA approved railings and ladder, demonstrating ARE’s ability to customize our systems to meet nearly any customer needs.
Project Benchmarks
- Crew flexibility and equipment availability allowing for installation under time constraints
- Limited space and access
- Above ground foundation required no digging on bed of rock
Project Resources
- 4-person crew
- 3 days
- Skid-steer
- Telehandler
- Local fill used for ballast
Challenges
- Limited space and access
- Quickly deployed in rain and wet conditions
- Rock base
- Foundation parts brought across 8T max weight bridge

Level site for foundation

Set your king-post and attach base trays

Attach truss arms onto base trays

Attach side walls and add ballast

Attach pole sections and raise pole with ARE Hydraulic Ram system